San Siro Stadium Project Cleared for Next Phase After Court Rejects Appeals

San Siro Stadium Project Cleared for Next Phase After Court Rejects Appeals

FolioPitch.com – 08 October 2026 | AC Milan and Inter have received a significant boost in their long-running efforts to build a new stadium, as the Lombardy Regional Administrative Court (TAR) rejected five appeals against the sale of the current San Siro and its surrounding land. The ruling, which brings to a close a dispute that began in 2022, means the GdS Design appeals construction sites what s next for the stadium project after key ruling can now move forward with renewed momentum. The court’s decision, published on Tuesday, saw four appeals declared inadmissible for procedural reasons and one dismissed on its merits, though all rulings can still be appealed to the Council of State by April 6.

The verdict represents a crucial milestone for the clubs, their owners Oaktree and RedBird Capital, and the City of Milan, all of whom are invested in the €2.3 billion project. With the legal hurdle cleared, attention can shift to the ambitious timeline that lies ahead. The GdS Design appeals construction sites what s next for the stadium project after key ruling has been a topic of intense speculation, and now the path is clearer for the next stages of development.

What Happens Next: Timeline and Key Milestones

Following the ruling, the schedule is expected to accelerate. Initial work has already begun in recent months, including the demolition of the south ticket office and some perimeter work. The next major event will be the presentation of the new rendering designed by Foster + Partners and Manica, anticipated between late October and early November. Alongside this, the Strategic Environmental Assessment (SEA) will be a critical step, with its opinion expected by mid-December. The environmental impact is substantial: 1.5 million cubic metres of earth to be excavated, 126,000 cubic metres of rubble, and tens of thousands of truck journeys.

The overall project carries a price tag of €2.3 billion. The main expenses break down as follows:

  • Approximately €700 million for the new stadium, which will seat 71,500 spectators.
  • €400 million for the hotel, shopping centre, and offices.
  • Another €400 million in financial costs, as the project will be funded through project financing.

Some issues remain unresolved, such as the fate of the current San Siro. Only a portion of the blue and orange sectors will remain standing, with the rest demolished and approximately 60,000 seats sold or given away to fans. The surrounding area plans range from a few buildings to an entirely green space. The GdS Design appeals construction sites what s next for the stadium project after key ruling also encompasses these unresolved questions, which will be addressed in the coming months.

Approval Process and Construction Timeline

After the environmental assessment, the next steps include the submission of the new Feasibility Plan and the approval of the Implementation Plan, which was submitted last March, by March 2027. In the meantime, the approval of the Conference of Services will be sought. The goal remains to complete the approval process by summer 2027 and then begin construction. The deadline for completion is set for June 2031, just in time to have a full season of matches before potentially hosting the European Championships in summer 2032.

The GdS Design appeals construction sites what s next for the stadium project after key ruling has been a complex saga, but the recent court decision provides a clear signal that the project is on track. Both clubs and the municipality are eager to see the new stadium become a reality, and the economic and sporting benefits are expected to be substantial.

Conclusion

The rejection of the appeals by the TAR marks a pivotal moment for the new San Siro project. While further legal challenges remain possible, the clubs can now proceed with greater confidence. The coming months will see crucial steps, from the unveiling of new designs to environmental approvals and the submission of key plans. If all goes according to schedule, construction could begin by 2027, with completion targeted for 2031. For Milan and Inter, the dream of a modern, state-of-the-art stadium is closer than ever, and the GdS Design appeals construction sites what s next for the stadium project after key ruling will continue to be a reference point for fans and stakeholders alike.

From the restless hum of Medan’s newsrooms, Demas Zac forged a writer’s instinct—sharpened by conversations with journalists who treated truth like poetry. Since 2017, he has turned the lens inward, observing how sci-fi dystopias mirror the rhythm of urban streets, finding sparks of hope in concrete corners. His words don’t just narrate; they dare you to see the future hiding in today’s quiet revolutions.